AI data centres' bottlenecks are proptech's opportunity

Updated: Nov 6

AI has made data centres Australia's biggest building category, writes Mark Hollands. Grid queues, local opposition and new federal government terms now decide what gets built, and technology firms are raising capital to solve each one.
Artificial intelligence (AI) has pushed data centres to the top of Australia's private non-residential building starts.
Work worth $18.2 billion began in the category in 2025–26, Green.com.au found in an analysis of Australian Bureau of Statistics (ABS) figures. That was more than three times the year before. Six years earlier, the category ranked 14th of 15 building types.
AI is the main reason. As many as 84% of new facilities may run AI workloads, a report for the Clean Energy Finance Corporation (CEFC) by consultancy Baringa found in December 2025. Commonwealth Bank (CBA) economists expect data centre investment to reach about $150 billion by 2030, and $260 billion within a decade.
But three things now decide which projects are built: a grid connection, the consent of the neighbours, and the federal government's terms. Each is an information problem, and Australian technology companies are raising capital to solve them. Sydney grid-modelling company Neara raised $90 million in February 2026 at a $1.1 billion valuation. Grid capacity software company Gridsight raised $36.3 million in September 2026, citing demand from data centres.
The neighbours are the most visible obstacle. In Melbourne's West Footscray, residents' objections to new power poles have stalled power to NextDC's M3, which its chief executive has called “Australia's largest hyperscale AI factory”. Goodman Group abandoned its $1.2 billion Project Mars data centre at Lane Cove in Sydney after community opposition and changes to regulation. In Perth, GreenSquare withdrew a $1.1 billion proposal at Hazelmere in May 2026 after almost 1,900 public submissions, most of them against it. On 31 October 2026, residents rallied in the Adelaide Hills against a proposed 1,200 megawatt (MW) AI data centre at Tungkillo.
The complaints are consistent: noise and fumes from diesel backup generators, water and power use, and buildings close to homes. Research by Australian software company Airteam and Primara estimated a nearby data centre could take up to $35,000 off a home's price, the ABC reported. In its survey of 1,000 Australians, 83% said they would not buy near a data centre without a discount.
Canberra sets the terms
In March 2026, the federal government released five Expectations for Data Centres and AI Infrastructure Developers. They are not legally binding, but energy-intensive proposals that do not closely match them will not be prioritised in Commonwealth regulatory assessments.
Developers are expected to secure new clean energy or storage to offset their demand and pay their share of grid costs. They are also expected to share energy consumption data, report their water use, and engage early with communities and First Nations peoples on where to build. The government is aiming for national standards by early 2027 that would make data centres add more new energy than they consume, AAP reported.
A Senate inquiry into AI and data centres heard calls from Sydney and Melbourne community groups for a moratorium on approvals. Independent senator David Pocock has proposed a 5% levy on the revenue of data centres with more than 5MW of IT load. He estimates it would raise about $500 million by 2030.
Power is the limit
The ABS category also holds other commercial buildings, but the figures show how slowly work is finished. For every dollar of work started in 2025–26, only 13 cents was completed, Green.com.au found, against 72 cents across private non-residential building. About $18.3 billion of work is still to be done, almost all of it in New South Wales and Victoria.
The Australian Energy Market Operator (AEMO) expects data centres to use about 13% of grid electricity by 2035–36, up from about 3% in 2025–26. Its 2026 Electricity Statement of Opportunities found more than 40% of proposed data centres had left the connection queue or slipped back in it since 2025.
NextDC showed on 21 October 2026 what a delayed connection costs. Jemena suspended parts of the network upgrade for M3 after residents objected to concrete power poles up to 22 metres tall, and will not restart before February 2027. NextDC took about $140 million out of its forecast net revenue for the 2027 financial year. Its shares fell about 42% that day.
Land with power is now priced accordingly. Research by JLL found data centre developers have paid 20.4% to 63.3% more than market value for land in outer suburban areas, and up to 182.1% more in South Sydney. “I’m just happy to sell my land at massive premiums to data centre developers,” Charter Hall chief executive David Harrison told the Property Congress in Brisbane on 21 October 2026.
The pipeline is far larger than what can be built. CBA counts about 23 gigawatts (GW) of announced capacity, but 76% of it is still in planning or at an earlier stage. Firmus, a Sydney-based developer of AI data centres backed by Nvidia, withdrew its planned ASX float on 9 October 2026, citing market volatility.
What it means for proptech
The gap between announced and buildable projects is where the opportunity sits. Planning consultancy Urbis says power and water constraints are “rarely visible through traditional site searches”. Four needs stand out in the figures.
Finding power. Neara estimates NSW's distribution network alone holds up to 10GW of capacity that is not being used, and works with close to 90% of Australia's network utilities. Gridsight, whose Australian clients include Endeavour Energy, says on average up to three-quarters of grid capacity is idle. Site intelligence tools have followed. Power Hungry tracks 23 Sydney data centre sites against the transmission grid. Data Centre Axis screens 683,150 Australian land parcels against published network capacity. Brisbane's Terrastack combines network, planning and land records to rank sites. Feasibility software company Popurise is expanding from residential into data centres, modelling IT load, power and capital cost per megawatt.
Winning consent. The federal expectations make early community engagement a condition of priority, and the Goodman and GreenSquare withdrawals show the cost of losing it. Open Point, owner of the Australian-founded engagement platform Social Pinpoint, has launched a single system to record community feedback and stakeholder commitments across large infrastructure projects.
Building. With about $150 billion to be spent by 2030, construction software is being sold to the sector. Procore markets data centre construction tools across Australia and New Zealand, and builder Nilsen used Revizto's model coordination software on NextDC's A1 Adelaide site. JLL found the construction sector leased 177,800 square metres of industrial space in the past year, its highest share of take-up since 2013.
Reporting and pricing. Developers will have to report energy and water use and show how they engaged communities. And the Airteam and Primara research suggests valuers, agents and residential property platforms will need to account for a nearby data centre when they price a home.
What to watch
NextDC will announce the outcome of its spending review by 20 November 2026, the date of its annual general meeting. Quantum DC has rescheduled its Tungkillo community consultations to 20 and 21 November 2026. A Victorian Government decision on further stages at M3 is not expected until after the state election on 28 November 2026. Firmus has until 15 December 2026 to lodge a complete proposal for its $2.1 billion Wesley Vale data centre in Tasmania.